Biomass Based Power Generation by Urjankur Shree Tatyasaheb Kore Warna Power Company Limited
#165of 196 in Biomass#8of 13 in Maharashtra India#286of 421 in Universal Carbon Registry (UCR)#39of 53 in ACM0006
Audit Analysis
This biomass power project in Maharashtra, India claims 92,235 tCO₂e over a 10-year crediting period using a jurisdictional baseline and a 2013 grid emission factor of 0.9 tCO₂/MWh. However, the evidence base is extremely thin: only a single PDD (dated 2025, after the crediting period ended) is available, with no verification report, monitoring report, or VVB assessment in the record. The absence of any additionality test documentation, verified emissions figures, or buffer pool arrangement leaves the core integrity claims unconfirmed.
Red Flags
- PDD is dated 2025-08-13, well after the crediting period ended on 2023-12-31, suggesting retroactive registration or a data anomaly that undermines the project's additionality and baseline assumptions
- No verification report, monitoring report, or VVB assessment appears in the evidence set — only the PDD is available, so the 92,235 tCO₂e claim is entirely unverified
- No additionality test type or VVB confirmation is found in the extracted record, leaving the project's additionality claim unsupported
- 0% leakage deduction is justified only as 'deemed negligible' without a documented analysis of alternative biomass fuel uses (e.g., cooking, industrial fuel) in the local supply chain
Credit Vintages
Issuance data not yet available — check back soon.
Risk Indicators
No test type or VVB confirmation found
No buffer pool; reversal data absent
0% deduction, 'deemed negligible' only
Jurisdictional method stated; no reassessment date
Mentioned; no FPIC or grievance mechanism
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →