Dak Lak Wastewater Treatment with Biogas System and Methane Recovery
#49of 111 in Biogas#19of 25 in Vietnam#435of 629 in Verra (VCS)#9of 22 in AMS-III.H
Audit Analysis
A VCS-registered wastewater-to-biogas project in Vietnam with a solid additionality assessment (combined test, VVB-verified) and inherently low permanence risk, but undermined by four contradictions between the PDD and validation report, a project-specific modeled baseline, absence of FPIC, and low extraction confidence across the document set. The ERR figures are internally consistent, and the 0% leakage deduction is reasonable for a biogas capture project, though the original PDD did not address leakage at all.
Red Flags
- Four contradictions between the PDD (2021) and validation report (2023) on baseline type, additionality test, leakage treatment, and crediting period length — the PDD originally proposed a 21-year crediting period (2022–2043) while the registered period is only 7 years (2023–2030)
- Free, Prior and Informed Consent (FPIC) was not conducted, despite the project treating community wastewater in Dak Lak province
- Minimum extraction confidence is rated low, and one of the eight source documents is of unknown type, reducing reliability of the extracted record
- Eight Corrective Action Requests were raised during validation (all closed), indicating the initial submission had notable gaps
Credit Vintages
No issuances recorded on the registry.
Risk Indicators
Combined test, VVB-verified
Biogas capture – no storage risk
0% deduction, PDD originally silent
Project-specific, modeled, no reassessment date
Grievance mechanism present, FPIC not conducted
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →