Diaobingshan New-built 49.5MW Wind Power Station Project
#358of 1935 in Renewable energy#135of 1084 in China#227of 1459 in CDM (UNFCCC)#266of 1287 in ACM0002
Audit Analysis
A 49.5 MW onshore wind project in China validated under CDM methodology ACM0002 v17.0 by RINA Services, using a jurisdictional grid baseline and a 0% leakage deduction appropriate for renewable generation. The project shows no material findings or corrective actions, but the extracted record lacks explicit additionality test details and any verification-stage reports, and a grid emission factor discrepancy between the validation report and an appendix warrants attention.
Red Flags
- Grid emission factor differs by ~18% between the validation report (0.9547 tCO₂/MWh) and an undated appendix (1.1291 tCO₂/MWh); the VVB's lower value was privileged as the authoritative figure, but the discrepancy suggests inconsistent data handling across project documents.
- Additionality test type and explicit VVB confirmation are absent from the extracted record; while RINA Services would have assessed additionality as part of CDM validation, the specific test (investment, barrier, or regulatory) is not documented in the available data.
- No verification-stage reports appear in the document set (only a validation report, PDD, and an appendix), limiting the ability to confirm that actual generation matched the ex-ante estimate over the full 2016–2023 crediting period.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2010 | 56,323 | 0 | 56,323 | |
| 2011 | 77,160 | 0 | 77,160 | |
| 2012 | 143,805 | 0 | 143,805 | |
| 2013 | 17,887 | 0 | 17,887 | |
| 2014 | 76,350 | 0 | 76,350 | |
| Total | 371,525 | 0 | 371,525 |
Risk Indicators
Test type not stated in extracted record
Avoidance project – no reversal risk
0% – negligible, appropriate for wind
Jurisdictional, reassessed 2017
Mentioned; FPIC and grievance mechanism not stated
CORSIA and CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →