Heilongjiang Wangkui 50MW Level Biomass Cogeneration Project
#201of 352 in Biomass#939of 1084 in China#1255of 1459 in CDM (UNFCCC)#31of 81 in ACM0006
Audit Analysis
This CDM biomass cogeneration project carries severe integrity concerns: the verification report documents that the plant was converted from cogeneration to power-only operation, equipment deviated from the registered PDD, and unregistered biomass types were introduced, all requiring a PDD revision. The project delivered approximately 167% of the pro-rata ex-ante expectation for the elapsed monitoring period, a figure that is difficult to reconcile with a project whose fundamental design changed mid-crediting. Combined with a project-specific baseline anchored to a 2004 grid emission factor and a 0% leakage deduction whose justification is inconsistent across documents, the over-crediting risk is material.
Red Flags
- Verification report (2016) records that the project changed from cogeneration to a power-only plant, a fundamental design deviation from the registered PDD that invalidates the original baseline and additionality framework
- Boiler, turbine, and generator specifications in the monitoring report are inconsistent with the registered PDD, and additional biomass types (wood residue, rice husk) were used beyond what was registered
- Verified ERR of 198,341 tCO₂e for the 2013–2015 monitoring period represents roughly 167% of the pro-rata expectation (~118,800 tCO₂e) derived from the 377,593 tCO₂e lifetime claim, raising over-crediting concerns especially given the operational changes
- Grid emission factor of 0.996 tCO₂/MWh is drawn from 2004 data and has not been updated, undermining baseline accuracy for a project operating through 2016
- No heat supply contract existed at the time of validation, yet the project was registered as a cogeneration project claiming reductions from both heat and power
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2012 | 364,406 | 0 | 364,406 | |
| 2014 | 267,651 | 0 | 267,651 | |
| 2016 | 377,593 | 0 | 377,593 | |
| Total | 1,009,650 | 0 | 1,009,650 |
Risk Indicators
VVB-confirmed barrier test, but project design changed post-
feedstock sustainability not document
0% deduction; justification inconsistent across documents
Project-specific baseline; grid EF from 2004 not updated
Safeguards and benefit sharing mentioned; FPIC and grievance
CORSIA and CCP status not stated in available documents
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →