Aprosacao Reforestation Project: community reforestation and agroforestry with small-scale cocoa farmers in Honduras.
GS-1808 ↗ · current registry ID: GS5012
#10of 38 in ARR (afforestation)#303of 426 in Gold Standard (GS)
Audit Analysis
The Aprosacao Reforestation Project in Honduras is a community-based agroforestry initiative with verified additionality, a 20% buffer pool, and quantified leakage, but it is undermined by a project-specific baseline, 14 corrective action requests at verification, and a severe discrepancy between the ex-ante ERR estimate and the verified monitoring figure (roughly 8× the pro-rata expectation). CORSIA eligibility without a stated CCP status adds dual-channel risk, and the overall evidence base, while broad (26 documents), carries medium extraction confidence.
Red Flags
- Verified ERR of ~94,953 tCO₂e for the 2018–2023 monitoring period is approximately 8.3× the pro-rata expectation derived from the PDD lifetime estimate of 118,691 tCO₂e over 50 years, raising serious over-crediting concerns.
- The PDD (June 2019) states a lifetime ERR of 118,691 tCO₂e while a September 2019 appendix states only 18,655 tCO₂e — a 6.4× discrepancy between two documents from the same verification cycle.
- 14 corrective action requests (CARs), 2 critical-level findings, and 3 further-action requests were raised by ECOCERT during verification, indicating substantial design or MRV deficiencies at the time of certification.
- Reversal risk was marked as 'not addressed' in the 2019 verification report; the 2024 monitoring report later states no reversal events, but the initial gap is a documentation weakness.
- CORSIA eligibility is confirmed while CCP status is not stated in any available document, leaving the dual-channel allocation question unresolved.
Credit Vintages
| Issued | Retired | Available | ||
|---|---|---|---|---|
| 2016 | 805 | 0 | 805 | |
| 2017 | 8,100 | 0 | 8,100 | |
| 2018 | 9,750 | 0 | 9,750 | |
| Total | 18,655 | 0 | 18,655 |
Risk Indicators
Combined test verified by ECOCERT
20% buffer pool; reversal not addressed in verification
0.2% quantified deduction
Project-specific; no reassessment date stated
FPIC, grievance mechanism, safeguards documented
CORSIA-eligible; CCP status not stated
⚑ Dispute this rating
Are you the project owner?
Metadata correction (free)
Name, country, marketplace or links incorrect? Let us know.
Does not modify the score.
[email protected] →Pipeline re-run with new documents
Have updated documentation not yet included? You can request a new run of the pipeline with the new inputs.
Submit Documents →